The Wisconsin Department of Transportation provides weekly road construction updates for road construction projects in Northeast Wisconsin. Construction project websites and this update can be found at https://projects.511wi.gov/region/north-central.
Shawano County
State Highway 47-55
Location: Shawano Creek to Menominee County line
Schedule: June 22 to September
Cost: $4,176,346.71
Description of work: Resurface the highway and widen paved shoulders. Modify the intersections with County Road H, Maple Avenue, Frailing Lane and County Road A to improve traffic operations. Replace pavement at the railroad crossing and install new signals and gates. Reconstruct curb ramps to meet current ADA requirements and spot repair of curb and gutter. Rehabilitate the surface on the bridge over Shawano Creek.
Traffic Impacts: Flagging operations at various locations throughout the project.
Anticipated work scheduled for next week: Crews will continue working on removals/grading of Curt Black Road working north through widening section towards the county line. Crews will also try and work on Anderson Avenue intersection later in the week. Paving crews will be on site fine grading and paving Frailing and Maple intersections. Paving crew will also pave widening areas from north of County Road H to Frailing, including BP gas station driveways. Mainline milling and paving operations began July 27. Concrete crews might be on site to pour curb and gutter, sidewalk and various curb patches. Landscapers continue to be on site working on restoration including seeding, mulch and e-mat in areas grading contractor has completed.
Website: https://projects.511wi.gov/wis47shawano
State Highway 55
Location: Outagamie County Line to County Road S
Schedule: This project is complete.
Work continues on state highways 47 and 55