The Oconto Falls School Board made it official April 3, approving a contract with the consulting firm that has been working with the school district on the recently approved referendum and ensuing projects.
The contract with Nexus Solutions covers architectural, engineering and construction management of the new middle school, roof work, and secure entrances approved in a $37.6 million referendum question in November.
The school board got a first look at the documents March 27 and had some concerns, and so did Geoffrey Lacy, a Green Bay attorney hired to review the contracts for the school district, according to Kim Sinclair, the district’s finance director, and said the firm was more than willing to accommodate those concerns.
For example, Sinclair said Nexus wanted 10% of the $37.6 million paid to them up front so they would have the money to start paying sub-contractors.
“We didn’t want to give them that much money up front, and they agreed to bring that down to 5%,” she said. “All the different areas where Geoff had stated, ‘We’d like to add this sentence,’ or that they went through, and they did that.”
Superintendent Dean Hess said Nexus, a Madison-based company that specializes in education and municipal facilities projects, has been “thoughtful and pro-active” in addressing issues that could come up.
“We vetted Nexus before we went forward with them,” Hess said. “Talking with different school districts that have worked with them ahead of time, one of the biggest pieces that kept coming back was the fact that ‘Nexus is there to represent the district.’ So obviously there’s a cost for their services, which we understand and we accept that.
“By the same token, they’re there and they’re bringing the professional capacity of the people on their team — whether it be from an architectural standpoint or an engineering standpoint or construction experience standpoint —to represent the best interests of our school district.”
Nexus plans to have a representative on site throughout the construction process and provide regular interaction with the district, including weekly updates pics and dialogue to share with community, staff and students, Hess said.
“I appreciate their willingness to be flexible and address some of the things we brought to their attention,” he said.
Lacy said he has worked with Nexus on a number of different school district projects, some much larger and some much smaller than this one.
“A lot of the final product here, from a contract standpoint, comes from revisions that I’ve worked with Nexus through previously in different school districts, so we benefit I think a little bit from having some of that stuff cleaned up before it ever even came to Oconto Falls,” Lacy said.
The goal is to make sure that as many dollars as possible go to the actual costs of construction, he said.
“The big thing moving forward is going to be watching the budget, watching the budget updates and so forth,” Lacy said. “Nexus is also going to bid out 100% of the work, which is ultimately to the district’s benefit because everything’s going to be competitively bid. Overall, their contracts are far more reasonable than a lot of construction contractor contracts, at least in the school district space that we spend a lot of time dealing with these contracts.”
The attorney said he was pleased with the cooperation he received working with the Nexus representatives.
“They’ve been more than willing to make revisions where we needed them,” Lacy said.
After reviewing the fine details of the contract for about a half-hour, the board voted unanimously to approve the contract.
The new middle school is to replace aging Washington Middle School in Oconto Falls, parts of which are more than a century old. A design team is working to finalize plans for the new middle school across County Road I from Oconto Falls High School.
The Oconto Falls City Council on March 14 approved annexing more than 90 acres of school district-owned land from the Town of Stiles. About half the property is expected to be used for the middle-school campus; there has been no discussion about using the rest of the land.
The goal is to open the new facility for the 2025-26 school year.