A domino still needs to fall before a solar energy farm can be introduced to Shawano.
The solar energy farm, which was approved by the Shawano County Board of Supervisors in 2021, would be run by National Grid Renewables and could produce more than 50 megawatts of solar energy. That, in turn, could provide the county with more than $8 million in revenue over the course of the lease. The lease is set to run for up to five years of development, two years of contruction and an extension term of 25 years. There is an added option that could potentially extend the lease up to another 30 years.
According to Tom Kautza, who is a part of the Public Property Committee for Shawano County, the county is waiting for National Grid to apply to American Transmission Company (ATC) in order to pump 99 megawatts into ATC’s transmission main line.
“That stuff takes forever, because ATC has to get permission from Midcontinent Independent System Operator (MISO), who I believe controls the power grid for a portion or all of 13 states in the Midwest and Manitoba, Canada,” said Kautza. “ATC then owns the lines, and MISO controls the power of what can can come in and where. So, they have to get permission to pump 99 megawatts at that point.”
Kautza said that National Grid is renting farmland right now in Belle Plaine to have the rights to potentially develop a solar farm, if and when it is approved.
“We did make an agreement with them that when they do start construction, the rate changes to $825 an acre,” said Kautza. “Then there is a payment that would come back to the county from the state for the equipment that is there on the land. The equipment is not assessed, but if you have a power generating facility, then you get reimbursement from the state for what the tax would be like on that equipment.”
Kautza said that National Grid has five years to figure out the logistics of the solar farm. He added that neither the county nor National Grid has determined where any of the solar panels will go yet.
“A lot of people thought that we are going to cut the woods down,” but that hasn’t been determined, he said. People think “so hunting is gone, that the ski hill and the tubing hill are going to be gone, too — none of that has been discussed yet,” Kautza continued. “Once they get their approvals, we will sit down and see just how big it will be and where we are going to let them put panels. That all has to be determined yet.”
He said that the next step in the process is to wait for MISO to let ATC know if they can pump 99 megawatts into the transmission main. Following that, the county can discuss the next step in the process.