The Oconto Falls City Council awarded bids Feb. 8 on one of two construction projects being funded by Community Development Block Grants, but the council rejected bids on a second, with one alderman having strong words for the city’s consulting firm.
Advance Construction of Green Bay submitted the lowest of eight bids received for the complete reconstruction of Park Avenue, including one alternate bid that substitutes corregated polyurethene storm sewer pipe for PVC.
Craig Schuh, manager of the civil engineering department for Ayres and Associates consultants, said the alternates were sought because of supply-chain issues that drive up prices of harder-to-find materials. Going with the alternate saves the city about $10,700, Schuh said.
Advance Construction will do the job for $743,720 after the council’s unanimous vote.
Schuh had less positive news for aldermen regarding the other project, renovation of the Oconto Falls Senior and Community Center on Caldwell Avenue. Three bids were received for the project, and the low bid of $1,065,000 was about $225,000 higher than expected.
Key components of the proposed renovation are a canopy over the front entrance, to allow seniors to enter from a vehicle under cover, and a new elevator to improve access to the basement. The only way that people in wheelchairs can reach the basement now is in a cramped freight elevator, in effect making half of the center’s 50,000 square feet inaccessible to people with disabilities.
Alderman Mat McDermid said Ayres should have offered contractors the opportunity to make an alternate bids to lower the overall cost, much as they did with Park Avenue. One alternate could have eliminated improvements to the basement gathering areas, for example, an important but not necessarily essential part of the job.
“To have this come in $225,000 over what the budget was is completely unacceptable,” McDermid said. “I understand volatility of the marketplace, but you have to have some foresight to see this coming.”
McDermid said having alternate bid options for the senior center would have allowed the city to “pick and choose here today and have this project going forward,” but instead it will be delayed as the project is rebid.
Schuh said his company would start work on the new bidding process the following morning.
The city has scheduled a public hearing on both projects for 6:30 p.m. March 8 in the council chambers at City Hall, 500 N. Chestnut Ave., Oconto Falls, to provide an update on the progress of both the senior center improvements and Park Avenue reconstruction projects and to give citizens the opportunity to provide input.
The grants are from the state Department of Administration through the Community Development Block Grant-CLOSE program — so named because the money comes from the now-closed revolving-fund loan program that CDBG once funded.
The city needs to complete the work by this fall before the grant expires. City Administrator Vicki Roberts said there is still plenty of time even with the delay in bidding.