The Shawano School Board postponed a plan on April 5 to have Elexco improve and upgrade the pipes at Shawano Community Middle School to prevent ongoing flooding of the parking lot and basement areas.
The project is expected to cost more than $400,000 and would begin work this summer, when the school’s foot traffic is drastically reduced. The board will take up the issue again at its April 19 meeting.
Shawn Mathwich, buildings and grounds director for the Shawano School District, told the board that the flooding has been an ongoing issue. It was a major problem for the first few months of his job, which he took over from Jeff Easter last year.
“My first couple of months working for the district, we ran into some water problems at the middle school,” Mathwich said. “After doing a little research and talking with people who’ve worked in the district for some time, we figured out we had a pretty substantial water issue.”
The district contacted Elexco, a firm based in Seymour, and had the company do some camera work to look at what was causing the flooding. Mitch Dorn, spokesman for the firm, found cause for concern in that the flooding could be damaging the boiler room equipment, producing mold and even undermining the school’s foundation.
The investigation found vegetation penetrating multiple joints in the system, an ample amount of sediment, and certain connections that are improperly sloped and provide limited access for cleaning and inspection, according to Dorn.
“Thirteen of the 41 joints were damaged with vegetation protruding through them,” he said. “The storm main was functional, as there was water flowing through the main out to the road (Union Street). But it was not functional at the capacity that it was designed for.”
Sediment was significantly present in the piping near the boiler room, causing almost 40% blockage, according to Dorn. Some roof drains on the southwest side have some concrete fragments in the piping and some damage present, he said.
“There’s no smoking gun, no major breaks,” Dorn said.
The remedies offered by Dorn include using a sewer jetter to regain capacity in the pipes and creating basins to catch sediment at the mouth of the tunnels, as well as one near the entrance of the school that would allow standing water to discharge to the streets. He is also recommending rerouting surface waters away from the school with the installation of a new perimeter storm main.
Dorn said the project would extend the school’s storm system to the north to reduce the subsurface water that Elexco discovered. It would also replace pipes in the areas where the concrete fragments have caused damage.
The school’s life expectancy after the renovation work five years ago is still another 25 years, but board member Chris Gull suggested that the district implement all the recommendations and not do it piecemeal.
“We spent so much money on that building, expecting to get 30 years out of it,” Gull said. “Don’t put a Band-Aid on it. Let’s fix the problem and get our 30 years out of this building.”